* Place of auxiliary mounting anchors to the buried steel, ,
*After the completion of the survey work of the buried anchors, anchor orders will be placed and production will begin,
*Buried anchor elements will be assembled in the first place accompanied by the topograph, * A 30 mm Grout margin will be left under the anchor plates. After the mounting is completed, graut filling will be done,
*In the mounting phase, first of all, assembly is done according to the axis and elevation according to the order specified in the work program,
*Place of the anchor system *Place of the columns,
*Place of the main beams,
*Place of the intermediate beams ,
*Completion of the bolts of the system by tightening it to the desired value ,
*Paint retouching ,
* Temporary delivery.