* Place of auxiliary mounting anchors to the buried steel, ,
*After the completion of the survey work of the buried anchors, anchor orders will be placed and production will begin,
*Buried anchor elements will be assembled in the first place accompanied by the topograph, * A 30 mm Grout margin will be left under the anchor plates. After the mounting is completed, graut filling will be done,
*In the mounting phase, first of all, assembly is done according to the axis and elevation according to the order specified in the work program,
*Place of the anchor system *Place of the columns,
*Place of the main beams,
*Place of the intermediate beams ,
*Completion of the bolts of the system by tightening it to the desired value ,
*Paint retouching ,
* Temporary delivery.

Measures to be Taken at the Mounting Site;

1- In the mounting area; Having a job site supervisor (Civil Eng.) responsible for occupational safety, supervisor, foreman will be good in terms of quality and safe assembly.
2- Before starting the assembly around the assembly area, guardrails or strip tapes and warning signs must be hung for work safety.

Responsibilities that the Administration will Provide During the Assembly Stage; Site;

* Stock area
*Crane installation site
*Preparation of the mounting site
*Mounting occupational safety
*Electricity
*Water